New Build in Surrey
Comparing the demands
Our choice to use a project manager was driven by the following factors
Eliminate key man risk/Diversification:
By engaging a main contractor, we felt that we were placing our eggs in one
basket, and if there was a breakdown in relationship between us, we would
have to engage another main contractor to take over the whole job (with cost
and time implications). We would also be at the mercy of the main
contractor's priorities and limited to the availability of his workforce (a
main contractor typically has to juggle more than one job to generate a
reasonable income). Conversely with the project manager/subcontractor route,
if there were any issues with one subcontractor (that couldn't be resolved
by the project manager), we would have to replace just that subcontractor.
Timeliness of (proceed-able) quotes:
Our architect was based within the M25 as were the builders he used and
recommended. Prior to starting the project (early 2016) we obtained quotes
from these builders but were typically looking at a year for them to be
available, such was the demand. In contrast, Vince Holden was able to source
quotes within a couple of weeks (and schedule project start when it suited
us) - subcontractors being less likely to be booked up months in advance.
Reduced duration of project:
A main contractor is likely to have a small (employed) workforce that he
calls upon, and this relatively limited amount of manpower can hinder
progress of the job. In contrast, by undertaking the PM/subcontractor route
(and with efficient planning) - it was possible to get multiple teams of
people working on the job at any one time (we counted 18 tradesmen over the
course of one day!).
Costs - flexibility:
Using a PM granted me more flexibility on various items of the project that
allowed cost savings while still achieving the same level of quality. For
example, we agreed that replacing the water main using a mole rather than
digging a trench would be just as efficient and would provide a reasonable
cost saving - all that we had to do was schedule in a subbie for that piece
of the work. With a main contractor my perception would be that he would
want to do things his own way.
Costs - absolute:
Breaking the quotes into specific subcontractor schedules of work allowed me
to benchmark the numbers against those provided by my QS and see where we
may be able to introduce optimisations. We felt that this was a more cost
efficient approach that the main contractor route. Having the experience of
a PM on board allowed us to introduce cost savings that the architect may
not have thought about - using tiles other than Spanish slate on the roof was a
significant saving.
Independent judgement on the quality of work:
Having someone on board with a large amount of building experience that was
representing us provided a great deal of comfort, both during each piece of
work (for example agreeing with ground-workers the best routing for the
drains) to agreeing a definitive snagging list when work was complete.
Quality of tradesmen:
It makes sense for a PM to have a contacts book full of subbies he can trust
as this will most likely require less intervention from him and he can have
an easier life! Various people that came to see the build as it progressed
were impressed with the quality of work and our neighbours commented on how
friendly and considerate the builders were.